Purchasing report

Purchasing report screen in Octibiz

Overview

The report presents external costs per project, supplier and brand as a target-versus-actual comparison. Six figures:

FigureMeaning
Open purchase ordersnot yet completed
Overdue purchase ordersdelivery deadline exceeded
Committed (target)volume bindingly promised
Actual costswhat has actually been incurred
Order volumenet of the binding orders
Open commitmentbudget minus actual of the still open orders

The gap between committed and actual is the real message. It shows what is still to come — and thereby makes visible whether a project budget is already spent even though the invoices have not arrived. That is where projects usually become expensive by surprise.

Core tasks

Read by project. The table shows project, committed, actual, variance and the number of purchase orders.

Read by supplier. The same breakdown by supplier — the view in which dependencies and price trends show up.

Chase the overdue. The overdue purchase orders figure is the day's action list: a missed delivery deadline means somebody has to follow up.

Note the external reconciliation. Where a reconciliation with bookkeeping is configured, the report shows the actual costs recorded there separately.

Fields in detail

This page has no input mask — it reports on the purchase orders. The selection at the top cuts the report, not the data.

FigureWhat it comes fromWhat it means
Perioddate pickers Ordered from/untilWhich orders are included, counted by order date.
Supplier / project / brandselectionThe cut of the report. The brand only works within the brands in which you may see the report — a foreign brand yields nothing.
Order volumenet of the binding orders (approved, sent, partially or fully delivered)What was commissioned.
Open commitmentbudget minus actual of the orders not yet completed (never negative)What is promised but not yet invoiced. The figure missing from a cash forecast when nobody keeps it.
Actual costactual of the orders: sum of the assigned incoming invoices, otherwise recordedActualCostWhat was really incurred.
Varianceactual against budgetWhere it became more expensive than approved. The real question of the page — not how much was bought, but how accurately it was planned.
Per brandtotals per brandHow external costs are distributed across brands.
Per suppliertotals per supplierWhere the volume sits. The basis for negotiation and for the question of where a dependency is forming.

Settings & permissions

  • Module module.procurement.
  • Permission procurement.report.view.
  • Attribution happens on the purchase order. Without a project reference, an order does not appear

in the project view, see Purchase orders.

  • Drafts do not count towards committed — only approved orders are binding.

FAQ & troubleshooting

A project is missing from the breakdown. Then no purchase order references it.

Committed is high, actual is zero. Normal for running orders: promised but not yet invoiced. That gap is exactly the warning the report delivers.

The variance is negative. Then actual costs exceed what was promised — check supplements and the tolerance on the orders concerned.

The report shows less than expected. It follows your view of purchase orders and projects. Anyone allowed to see less sees smaller totals.

procurement.report · Available from version 0.5.0