Purchasing report

Purchasing report screen in Octibiz

Overview

The report presents external costs per project and supplier as a target-versus-actual comparison. Four figures:

FigureMeaning
Open purchase ordersnot yet completed
Overdue purchase ordersdelivery deadline exceeded
Committed (target)volume bindingly promised
Actual costswhat has actually been incurred

The gap between committed and actual is the real message. It shows what is still to come — and thereby makes visible whether a project budget is already spent even though the invoices have not arrived. That is where projects usually become expensive by surprise.

Core tasks

Read by project. The table shows project, committed, actual, variance and the number of purchase orders.

Read by supplier. The same breakdown by supplier — the view in which dependencies and price trends show up.

Chase the overdue. The overdue purchase orders figure is the day's action list: a missed delivery deadline means somebody has to follow up.

Note the external reconciliation. Where a reconciliation with bookkeeping is configured, the report shows the actual costs recorded there separately.

Fields in detail

This page has no input mask — it reports on the purchase orders. The selection at the top cuts the report, not the data.

FigureWhat it comes fromWhat it means
Perioddate pickersWhich orders are included, counted by order date.
Supplier / project / brandselectionThe cut of the report.
Order volumesum of order valuesWhat was commissioned.
Open commitmentorders in a category counting as openWhat is promised but not yet invoiced. The figure missing from a cash forecast when nobody keeps it.
Actual costrecordedActualCost of the ordersWhat was really paid.
Varianceactual against budgetWhere it became more expensive than approved. The real question of the page — not how much was bought, but how accurately it was planned.
Per suppliertotals per supplierWhere the volume sits. The basis for negotiation and for the question of where a dependency is forming.

Settings & permissions

  • Module module.procurement.
  • Permission procurement.report.view.
  • Attribution happens on the purchase order. Without a project reference, an order does not appear

in the project view, see Purchase orders.

  • Drafts do not count towards committed — only approved orders are binding.

FAQ & troubleshooting

A project is missing from the breakdown. Then no purchase order references it.

Committed is high, actual is zero. Normal for running orders: promised but not yet invoiced. That gap is exactly the warning the report delivers.

The variance is negative. Then actual costs exceed what was promised — check supplements and the tolerance on the orders concerned.

The report shows less than expected. It follows your view of purchase orders and projects. Anyone allowed to see less sees smaller totals.

procurement.report · Available from version 0.5.0