Requests for quotation

Requests for quotation screen in Octibiz

Overview

A request goes to several suppliers and is then compared and awarded line by line. The list shows request, deadline, participating suppliers and status.

Awarding line by line is the point: one supplier is rarely the best at everything. Awarding a whole request to one means overpaying on half the lines.

Core tasks

Compare. Per line, the quotes appear with supplier, price, lead time in days and line value. The cheapest quote is marked.

Read the hint correctly. The application says it itself, plainly: "cheapest" is a hint — the ability to deliver and reliability appear in none of these figures. Awarding on price alone buys the supply bottleneck along with it.

Watch minimum quantities. Where the minimum order quantity exceeds the requirement, the line says so. The cheaper unit price can then cost more than the dearer one without the surplus.

Award and order. Award and order turns the awarded lines into draft purchase orders — one per supplier.

Fields in detail

The What it does column answers what changes in the system — not what the field is called. The grey name behind the label is the API field: the same thing runs under that name through automation, import and AI tools.

Creating a request for quotation

FieldRequiredValues / formatWhat it does
Title titleyestext, max. 160 charactersWhat it is about. It becomes the subject of the request to the suppliers.
Items itemsyesarticles with quantityWhat is asked for. Without a price — that is precisely what the supplier is meant to state.
Suppliers supplierRoleIdsyesseveral suppliersWho is asked. They all get the same request; the answers later stand side by side and can be compared.
Answer by dueDatenodateBy when you expect an answer. It appears in the request and makes following up defensible.
Note notenotextWhat the suppliers are additionally told — quality requirements, delivery terms, anything else.
Brand brandIdnoone of your brandsWhich brand is asking.

From the cheapest or most suitable answer an order is created in one step — the items are carried over rather than retyped.

Settings & permissions

  • Module module.purchasing.
  • purchasing.order.create for the resulting orders.
  • Lines without a quote stay open. The display states explicitly that nobody has quoted yet.
  • The deadline is a statement, not a lock. It structures the process; it does not prevent a late

award.

FAQ & troubleshooting

There is no quote for a line. Then no supplier bid on it. Follow up, or award the line separately.

The cheapest quote is not the best. Precisely why the hint is there. Lead time, minimum quantity and reliability belong in the decision.

After awarding, an order is missing. One order arises per supplier, not per line. Several lines to the same supplier land in one.

Can I withdraw an award? The resulting orders are drafts — carry on there rather than bending the request.

purchasing.rfqs · Available from version 0.5.0